Dholera building permission: how Form C, deemed approval and Building Use work
Updated 11 November 2026. Compiled by the Dholerapedia desk from the sources listed at the end of this page.
No building or structure may be erected or occupied inside Dholera SIR without the prior permission of DSIRDA, the regional development authority, applied for on Form C. If DSIRDA gives no order within three months, the permission is deemed granted. It stays valid for one year, extendable to three, and a Building Use permission is needed before the premises are used. Rules captured 4 August 2026.
The permission stages inside Dholera SIR
| Stage | What it is | Authority | Time limit on record | Fee on record |
|---|---|---|---|---|
| 1 | Approval to start the activity, where a unit or business is being set up | Apex Authority (Gujarat Infrastructure Development Board), then DSIRDA makes the land offer | Not stated in the Act ("as early as possible") | Left to Apex Authority regulations |
| 2 | Development permission, Form C | Chief Executive Officer, DSIRDA | Deemed granted if no order within 3 months | Not published |
| 3 | Validity of the permission | DSIRDA | 1 year, extendable one year at a time to 3 years in all | Not stated |
| 4 | Appeal against a decision | Disputes Resolution Forum, then Disputes Settlement Mechanism | 15 days for each appeal | Not stated |
| 5 | Building Use (BU) permission after completion | DSIRDA | Not stated | Scrutiny fee required, amount blank on the form |
From the Gujarat Special Investment Region Act 2009 (sections 8, 15, 16 and 18), sections 29 and 32 of the Gujarat Town Planning and Urban Development Act 1976 as they apply in the SIR, and DSIRDA's Form C and BU checklist, captured 4 August 2026. Stage 1 applies to new economic activity; stages 2 to 5 apply to any building.
Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.
Who grants permission
Dholera SIR is governed by the Gujarat Special Investment Region Act 2009, which created the Dholera Special Investment Regional Development Authority, DSIRDA. Section 15 of the Act, read with the town planning law of the state, makes DSIRDA the authority that grants development permission. A separate Apex Authority, the Gujarat Infrastructure Development Board, is the single point of contact for a new unit or economic activity, and its approval comes before DSIRDA offers land. A buyer who only wants to build a house deals with DSIRDA. Our page on DSIRDA explains how the authority is set up.
Where the building controls and the single window sit
DSIRDA's FAQ page says it handles approval of development plans and the framing of general development controls and regulations, and points to the General Development Control Regulations for coverage and development controls. It directs investors to the Gujarat government's single-window Investor Facilitation Portal for statutory approvals. For land, the same page says industrial plots are allotted by first-come first-served, auction or tender, and residential and commercial plots by auction or tender. Read the regulations for the zone your plot falls in before you design, because the Form C asks for plan details that must fit them.
What Form C asks for
Form C is the application for development permission under sections 8 and 15 of the SIR Act and sections 27, 34 and 49 of the Gujarat Town Planning and Urban Development Act 1976. It is filed with the Chief Executive Officer of DSIRDA with a scrutiny checklist. The form asks for the name, address and registration number of the registered architect or engineer, the structural engineer and the clerk of works. It also asks for the plot's location: the village name, town planning scheme number, revenue survey number, original plot number, final plot number, any final plot deduction and the sub-plot number, each with areas in square metres.
That plot detail is why the plot must be traceable to a final plot in a sanctioned scheme. Read Dholera's town planning schemes to see how final plots are numbered.
Deemed approval after three months
Section 29 of the town planning law applies in the SIR with the necessary changes. If the authority does not communicate its order to the applicant within three months of receiving the application, the permission is deemed granted when the three months end. Deemed approval is a statutory clock, not a promise of speed. The record we hold gives no average time DSIRDA takes to decide, and we do not estimate one.
How long the permission lasts
Under section 32, a permission, granted or deemed, remains in force for one year and then lapses. The authority may extend it for periods of not more than one year at a time, up to three years in all. An owner who plans to build in stages should note that the clock runs from the permission, not from the date the money is ready.
If DSIRDA refuses or places conditions
An appeal against a DSIRDA decision goes to the Disputes Resolution Forum within 15 days, including public holidays, of the decision. A second appeal lies to the Disputes Settlement Mechanism within a further 15 days. The record does not give the forums' composition or how long they take, only the time limits to file.
Building Use permission before you occupy
After completion and before use, every person, unit or developer must obtain Building Use, or BU, permission from DSIRDA. Without it the building cannot lawfully be occupied. The published BU checklist asks for the approved layout, building plan and development permission, the 7/12 extract, undertaking bonds, working and structural drawings, a lift licence, a fire NOC, an airport NOC, an environment clearance, a structural stability certificate and five-year insurance for the construction. A sewer charge is also needed where the plot lies inside a town planning scheme. The checklist has a line for a scrutiny fee, but the amount is blank on the published form.
What is not published
The Form C fee, the BU scrutiny fee and the Apex Authority's proposal fee are not stated on any page we could open. DSIRDA's General Development Control Regulations may carry a fee schedule, but we did not retrieve that document, so we print no amount. For a plot-level answer, a buyer should ask DSIRDA directly, and read the regulations for the zone the plot falls in, as in our explanation of non-agricultural plots.
Questions people ask
Do I need permission to build a house in Dholera SIR?
Yes. No person may erect or occupy a building or structure inside the SIR without the previous permission of DSIRDA, applied for on Form C. After completion, Building Use permission is also needed.
What is deemed permission in Dholera?
If DSIRDA does not communicate its order within three months of receiving a Form C application, the permission is treated as granted when the three months end, under section 29 of the Gujarat Town Planning and Urban Development Act 1976 as applied in the SIR.
How long is a Dholera building permission valid?
One year, under section 32. DSIRDA may extend it by up to one year at a time, to a maximum of three years in all.
What is the fee for building permission in Dholera?
Not published. Form C carries no fee clause, and the amount on the BU scrutiny line is blank on the published form. Ask DSIRDA for the current schedule.
What is BU permission in Dholera?
Building Use permission, issued by DSIRDA after completion and before the premises are used. The checklist includes fire and airport NOCs, an environment clearance and a structural stability certificate.
Where can I appeal if DSIRDA rejects my application?
To the Disputes Resolution Forum within 15 days of the decision, and then to the Disputes Settlement Mechanism within a further 15 days.
Read next
- Dholera real estate
- DSIRDA, the development authority
- Dholera town planning schemes
- Non-agricultural plots explained
- The SIR Act 2009
Sources
- DSIRDA, Form C application for development permission (captured 4 August 2026)
- DSIRDA, Building Use (BU) checklist (captured 4 August 2026)
- Gujarat Special Investment Region Act 2009, sections 15, 16 and 18 (Gujarat Act No. 2 of 2009)
- Gujarat Town Planning and Urban Development Act 1976, sections 29 and 32 (as applied in the SIR) (read 4 August 2026)
- DSIRDA and DICDL, Frequently Asked Questions (read 13 November 2026)