Dholera's biggest numbers: the largest figure in each category, with its source and date

Updated 11 November 2026. Compiled by the Dholerapedia desk from the sources listed at the end of this page.

The biggest Dholera figures in the record are a planned area of about 920 sq km, a single investment of about Rs 91,000 crore at the Tata fab, a jobs target of about 800,000, a solar target of 5,000 MW and a fab capacity of up to 50,000 wafers a month. Each is marked as a plan, a target, an approval or a built fact, with its source and date.

How this list is rankedOne row per kind of measure, giving the largest figure that a named government or company source states for it. Figures cannot be ranked across different units, so rows are grouped by category, with the largest money row first. Each row says whether the figure is built, approved, planned or a target. Figures that only appear on broker pages are left out.

The biggest figure in each category

CategoryFigureKindSourceDate
Money in one projectAbout Rs 91,000 crore, Tata fabApproved investmentUnion Cabinet and the Press Information Bureau29 February 2024
Planned areaAbout 920 sq km, of which 422.42 sq km is the urban part divided into town planning schemesPlanDICDL and the Final Development PlanPlan sanctioned 10 September 2012
JobsAbout 800,000 at full development, split about 312,900 direct industrial and 483,630 indirectTargetDSIRDA Development Plan, DICDL websiteChecked November 2026
PopulationAbout 1 million residents at full build-outReported targetPromotional target for the third phase; not stated in the plan documents we hold, and published figures vary by sourceReported, 2026
Power5,000 MW solar, of which 1,000 MW sanctioned in Phase I and about 300 MW commissionedLong-range target; 300 MW builtNICDC monitoring report30 June 2026
Chip outputUp to 50,000 wafers a month on 300 mm wafersPlanned capacityCabinet approval and company statements29 February 2024
Industrial land11,000 hectares reserved for industry, which is 110 sq kmPlanDSIRDA Development PlanPlan
Land allotted so far14 plots, 545 acres, of which 476 acres industrialRecorded factNICDC monitoring report30 June 2026
Road109 km Ahmedabad-Dholera ExpresswayBuilt; inauguratedNHAI and national press31 March 2026
Rail134 km Ahmedabad-Dholera semi-high-speed line, about Rs 20,667 croreApprovedPress Information Bureau13 May 2026
Runway3,200 m single runway, Phase IBuilt; airport not openAirport company documentsTrial landing 4 June 2026
Water2,200 million litres raw water reservoir announced at an estimate of Rs 438.74 crore; no contractor namedProposedDeshGujarat3 November 2026

1. Money in one project

  • EntityTata Semiconductor Manufacturing
  • Cabinet date29 February 2024
  • Government support50 per cent of eligible cost under the India Semiconductor Mission

The Cabinet figure is about Rs 91,000 crore; one August 2026 report (Business Today) gives about Rs 91,526 crore, so the figure varies slightly by document. It is the largest single, well-sourced commitment in the record. Larger numbers that circulate, such as a Rs 6 lakh crore data centre target, are for the whole state, not Dholera.

2. Jobs

  • Direct industrialAbout 312,900
  • IndirectAbout 483,630
  • Largest sectorElectronics and emerging technology, 87,300

The direct and indirect numbers in the Development Plan add up to about 796,500, which is shown as about 800,000. It is a long-horizon target. An earlier target of 80,000 jobs by 2020 lapsed.

3. Planned area

  • Notified area (2009)879.34 sq km, 22 villages
  • Urban part422.42 sq km
  • Activation AreaAbout 22.5 sq km

The 920 sq km figure is a planning extent. Only the urban part is divided into schemes, and only the Activation Area has had its first roads and utilities built.

4. Power

  • CommissionedAbout 300 MW
  • Sanctioned Phase I1,000 MW
  • Long-range target5,000 MW, around 2030

Reports differ on whether the 300 MW Tata Power plant is the same 300 MW as the government figure, so we state the government report only.

How to read a big number

Each number has a kind. A built figure can be seen on the ground. An approved figure has a government order behind it. A plan or a target is a figure someone intends to reach. Mixing the kinds is how a target comes to be quoted as an achievement.

When you see a Dholera figure, find its row here. If it is not here, ask where it comes from.

Numbers left out

Plot prices per square yard and completion percentages from broker pages are not printed. The record has no reliable total for all money committed to Dholera, so none is given.

What this list cannot tell you

This list gives the largest stated figure in each category. It cannot tell you that any plan will be reached, or what any plot is worth.

Questions people ask

How big is Dholera in square kilometres?

The authority describes the planned region as about 920 sq km. The 22 villages in the 2009 notification add up to 879.34 sq km, and the urban part divided into town planning schemes is 422.42 sq km, from the 2012 Final Development Plan.

How much money is going into the Dholera fab?

About Rs 91,000 crore was approved by the Union Cabinet on 29 February 2024 for the Tata Electronics and PSMC fab. One August 2026 report (Business Today) gives about Rs 91,526 crore. Government support covers 50 per cent of eligible cost.

How many jobs will Dholera create?

The plan targets about 800,000 jobs at full development, around 2040 to 2042. The Development Plan splits this into about 312,900 direct industrial jobs and 483,630 indirect jobs. It is a target and not a forecast.

How much solar power does Dholera have?

About 300 MW was commissioned at 30 June 2026 out of 1,000 MW sanctioned for Phase I. The 5,000 MW figure is a long-range target for around 2030, not capacity in operation.

How long is the Dholera runway?

The Phase I runway is 3,200 m. A trial landing took place on 4 June 2026. The airport is not open as of 11 November 2026, with the end of 2026 reported as the target.

Read next

Sources

  1. Press Information Bureau: Tata fab approval and Cabinet decisions (29 February 2024 and 13 May 2026)
  2. DSIRDA and DICDL: about Dholera and the Development Plan (checked November 2026)
  3. NICDC Delivery Monitoring Unit report (30 June 2026)
  4. DeshGujarat: Dholera to get raw water reservoir (3 November 2026)