HomeEncyclopedia › Dholera Solar Park

Dholera Solar Park

Ultra-mega solar power park

See also Water · Utilities.
Dholera Solar Park
Ultimate target5,000 MW (~by 2030)
Phase-I sanctioned1,000 MW
Commissioned~300 MW (Tata Power)
AgencyGujarat Power Corporation Ltd

The Dholera Solar Park (Dholera Ultra-Mega Solar Power Park) is a large solar power project associated with the SIR.

Capacity and status

The ultimate announced target is 5,000 MW by around 2030, which is a target and not installed capacity. The NICDC ledger states that 300 MW of the 1,000 MW first phase, awarded to Tata Power, has been commissioned. Some secondary sources claim higher commissioned totals, which are not reconciled against the official figure, so the reliable number is about 300 MW operational. Confirmed

This article follows Dholerapedia's sourcing standard: every figure is tagged Confirmed (government or official), Reported (press or trade) or Unverified (broker), and dated. Anything framed as a future event is labelled a target until a government source confirms it. Where a fact is not reliably available, we say so rather than estimate. See the methodology.

Key facts

The core facts for dholera solar park are summarised below; each is drawn from the sources listed at the foot of this article and dated to the review month.

Context

Dholera SIR is planned over about 920 sq km, of which roughly 422 sq km is designated for urban development across six town-planning schemes phased over about three decades. It is governed by the DSIRDA (planning authority) and built by DICDL, a special purpose vehicle held 51% by Gujarat and 49% by the central government through the NICDC Trust, and it is the flagship node of the Delhi-Mumbai Industrial Corridor. This context frames every article on the region; the specifics of this topic are covered above, and the full picture is in What is Dholera SIR and the master plan.

Reading this reference

Dholerapedia is a reference, so it is built to be checked rather than believed. Every figure in this article is tagged by source, Confirmed for a government or official record, Reported for press or trade coverage, and Unverified for a broker claim, and each carries a date because Dholera changes and a number that was right last year may not hold now. Anything described as a future event is treated as a target until a government source confirms it, and where a fact is not reliably available the article says so instead of guessing. None of this is investment, legal or tax advice, and no government source guarantees appreciation. If you are evaluating a specific plot, the figures here are context, not a substitute for confirming that parcel's GUJRERA registration, title and price yourself. Corrections that improve accuracy are welcome via the contact page, and entries are updated as official figures change rather than left stale. The reason for this standard is simple: a reference is only worth reading if you can act on it and check it, so we would rather show a smaller number of well-sourced facts than a larger number of impressive-sounding ones. Where a claim about Dholera circulates widely but rests only on a broker source, we note it as unverified rather than repeat it as settled, and where the official record and the marketing disagree, we follow the official record. For the collected figures across the encyclopedia, see Dholera in numbers, and for the full method see the methodology.

References

  1. NICDC Delivery Monitoring Unit report, 30 June 2026 (DPIIT).
  2. CEA Solar Parks quarterly report (Sept 2025).
Categories: Energy · Dholera SIR